I have gotten started installing the wood finally after much reading on this site for the past year as we built our house. 3 1/4" red oak and 4" maple are the woods I am using, 3/4" thick and there is about 1000 sq ft all together. I have kind of a game plan (lots of gaps still) and wanted to run it by you guys first. There will be no staining.
The floor is looking pretty level as it is being laid, some edges stick up a slight bit, but not much.
I will rent a U-Sand Machine. Planning on the following:
U-Sand 40 grit -- shop vac -- tack
fill with Woodwise filler
U-Sand 80 grit -- shop vac -- tack
spot fill with Woodwise filler
U-Sand 100 grit -- shop vac -- tack
U-Sand Maple only with 160 grit -- shop vac -- tack
one coat of bonaseal
1 coat of traffic and then buff with U-Sand
2 coats of traffic
What changes would you make to above?
This is a new construction and we have baseboards and hand rail (which is on the oak) to put down after flooring is finished, then cabinets installed, and painting (including the trim). When would you sand the floors?
Should I buff again between the 2nd and final coat of Traffic?
I am thinking that I would like to go ahead and sand the floors now due to the staircase railing. I have some ridges where pieces of stair nosing meet and it would be much easier to do now insted after the railing is put up.
Lots of questions.
Thanks for any advice given.
Keith